Crack repairs to US 50 begin Dec. 4

HUTCHINSON, Kan. — Crews are scheduled to begin repairing cracks on more than eight miles of U.S. 50 in Reno County on Dec. 4.

The project will start on U.S. 50 from the four-lane/two-lane division east of Hutchinson and continue east to the Reno/Harvey county line.

Pavement Pros, LLC, of McPherson is the primary contractor for the $117,977 project. The contractor has 45 working days to complete the project.

Flaggers and a pilot car will control traffic.